Infrastructure Project Phase 1
To help keep residents and business owners informed, the City will post weekly construction updates as they become available. These updates will include information about the current schedule, upcoming work, and other items related to the project.
Updates are expected to be provided late Tuesday afternoons. If a weekly update is not available, any new information or notes will be posted below as they are received. Construction update flyers will also be available at the Post Office. Moore Engineering will prepare the update flyers, and the City will distribute them.
Key Notes
- The public is urged to use caution throughout this construction season and to stay clear of all construction equipment & areas being actively worked on.
- Please use caution when driving on the roads of the project. Not all roads will be passable with all vehicles at all times. Use caution when roads are muddy due to rain.
- There may be times of temporary water shut downs as the contractor is working on temporary hook-ups and main installations.
- Once the concrete is poured, it needs 7 days of cure time before any traffic is allowed on it. Please refrain from driving on any curb and gutter or driveways until after this time frame. Concrete can be walked on after 24 hours.
Project Contacts • Please utilize the following contacts for any Immediate Assistance, questions or concerns:
- Ben Roehl | 320-260-0927 | Lead Resident Project Representative
- Amber Muir | 701-200-4373 | Construction Administration
- Josiah Rostad | 218-770-1608 | Signing Engineer
CONSTRUCTION UPDATES
Residents and Businesses are encouraged to check back regularly for the latest project information
August 25, 2026
Weekly Update •The contractor will be working on the remaining concrete curb and gutter and driveways.
Looking Ahead • The paving contractor is scheduled to begin paving the week of August 31st.
Water Tower Update •The contractor will be completing soil remediation before continuing work on the sanitary sewer and water lines.
August 18, 2026
Weekly Update •The contractor will be continue working on restoring the project area and preparing for concrete and paving work.
Looking Ahead •The contractor will be working on the sub-cut on Pacific Avenue. There will be another crew working on the remaining concrete curb and gutter and driveways. The paving contractor is scheduled to begin paving the week of August 31st.
Water Tower Update •The contractor will be completing soil remediation before continuing work on the sanitary sewer and water lines.
August 11, 2026
Weekly Update •The contractor will finish sub-cutting on 6th Street and Pacific Avenue. They will continue working on the curb & Gutter.
Looking Ahead •The contractor will be working on grading behind the curb and gutter, as well as general cleanup around town. The concrete subcontractor will be back to complete the concrete work.
August 5, 2026
Weekly Update •The contractor will be working on the sub-cut on 4th Street and Pacific Avenue. They will also be spreading topsoil on 3rd Street and McLauglin Avenue.
Looking Ahead •The contractor will be completing the sub-cut on 4th Street and Pacific Avenue. There will be an additional crew beginning to pour the concrete curb and gutter on the south side of town.
Water Tower Update • The contractor will be starting work on the water tower foundation, which will take multiple months.
Related Documents
-
Infrastructure Project 20912 Phase 1
- Construction Update Phase 1 Improvements 8-25-26 ( PDF / 281 KB )
- Construction Update Phase 1 Improvements 8-18-26 ( PDF / 281 KB )
- Construction Update Phase 1 Improvements 8-11-26 ( PDF / 212 KB )
- Construction Update Phase 1 Improvements 8-4-26 ( PDF / 266 KB )
- Construction Update Phase 1 Improvements 7-28-26 ( PDF / 84 KB )
- Construction Update Phase 1 Improvements 7-21-26 ( PDF / 393 KB )
- Construction Update Phase 1 Improvements 7-14-26 ( PDF / 284 KB )
- Construction Update Phase 1 Improvements 7-7-26 ( PDF / 284 KB )
- Construction Update Phase 1 Improvements 6-30-26 ( PDF / 314 KB )
- Construction Update Phase 1 Improvements 6-23-26 ( PDF / 321 KB )
- Construction Update Phase 1 Improvements 6-16-26 ( PDF / 493 KB )
- Construction Update Phase 1 Improvements 6-9-26 ( PDF / 438 KB )
- Construction Update Phase 1 Improvements 6-2-26 ( PDF / 545 KB )
- Construction Update Phase 1 Improvements 5-26-26 ( PDF / 546 KB )
- Construction Update Phase 1 Improvements 5-19-26 ( PDF / 545 KB )
- Construction Update Phase 1 Improvements 5-12-26 ( PDF / 137 KB )
- Construction Update Phase 1 Improvements 5-6-26 ( PDF / 145 KB )
- Construction Update Phase 1 Improvements 4-28-26 ( PDF / 310 KB )
- Construction Update Phase 1 Improvements 4-21-26 ( PDF / 279 KB )
- Construction Update Phase 1 Improvements 4-14-26 ( PDF / 145 KB )
- Construction Update Phase 1 Improvements 4-7-26 ( PDF / 263 KB )
- Construction Update Phase 1 Improvements 3-30-26 ( PDF / 334 KB )